Project Dashboard

Status: ACTIVE MONITORING

  • NIRB File No:

    08MN053

  • Application No.:

    123910

  • Project Type:

    Mine Development

  • Project Name:

    Mary River Project

Applicant
Primary Contact
External Links

Mary River Project

Assessment Phase / Activity
  • Started project monitoring 2010-07-15
  • Technical advisor assigned 2016-01-29
  • NIRB Received Report From Proponent 2016-04-22
  • Annual Report: Commenting completed 2016-06-27
  • NIRB Notification to Proponents Received 2016-06-30
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2016-08-04
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-10-28
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-11-03
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2016-12-02
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-07
  • NIRB Notice to Parties re Proponent response received 2016-12-15
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-15
  • Issued Correspondence to Proponent Re Conformity Determination Required Prior to Potential Reconside 2016-12-19
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2016-12-21
  • NIRB issues notice of community information sessions 2017-03-13
  • NIRB issues notice of community information sessions 2017-03-14
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-06
  • NIRB Ltr to Parties requesting comments on report. 2017-05-31
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-05-30
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-04
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-28
  • NIRB Issues notification of planned site visit 2017-08-01
  • NIRB Ltr to proponent re additional information required 2017-08-21
  • NIRB Issues Correspondence to Parties re Project Certificate Terms and Conditions 2017-08-22
  • Send Notification to Parties 2017-08-31
  • Send Notification to Parties 2017-09-01
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-01
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-06
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-07
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-13
  • NIRB Ltr to proponent re additional information required 2017-09-22
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2017-09-29
  • NIRB Ltr to Proponent re reconsideration of Project Certificate 2017-10-26
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-11-17
  • NIRB Ltr to Proponent re Conformity Determination required 2017-11-14
  • NIRB Ltr to parties requesting comment on potential project certification reconsideration 2017-11-27
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-19
  • NIRB Notice to Parties re comments received 2017-11-30
  • Send Notification to Parties 2017-12-12
  • NIRB Issues notification of planned site visit 2018-03-16
  • NIRB Ltr to Parties requesting comments on report. 2018-04-23
  • NIRB Ltr to Parties requesting comments on report. 2018-05-14
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2018-05-30
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2018-07-12
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-06
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-11
  • NIRB Notice to Parties re receipt of Project Certificate Consideration Request 2018-06-26
  • NIRB Notice to Parties re receipt of final written submissions 2018-06-27
  • NIRB issues notice of community information sessions 2018-06-29
  • Send Notification to Parties 2018-07-10
  • NIRB Notice to Parties re comments received 2018-07-12
  • Send Notification to Parties 2018-07-17
  • NIRB Ltr to Parties re anticipated FEIS submission date 2018-07-19
  • NIRB Ltr to Parties re anticipated FEIS submission date 2018-07-26
  • NIRB Notice to Parties re receipt of final written submissions 2018-07-27
  • NIRB issues notice of community information sessions 2018-08-01
  • NIRB issues notice of community information sessions 2018-08-03
  • NIRB Notice to Parties re proponent response to final written submissions 2018-08-10
  • Guidelines: NIRB issues guidelines to proponent 2018-08-21
  • NIRB issues notice of receipt of final EIS submission 2018-08-23
  • NIRB Ltr to Minister(s) re Final Hearing Report 2018-08-31
  • NIRB Ltr to Minister(s) re Final Hearing Report 2018-08-31
  • NIRB Ltr to Proponent re FEIS Compliance Determination 2018-09-14
  • NIRB Received Minister’s decision re Final Hearing Report 2018-10-02
  • NIRB Received Minister’s decision re Final Hearing Report 2018-10-02
  • NIRB issues notice of receipt of final EIS submission 2018-10-10
  • NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments 2018-10-12
Region
  • North Baffin
Project Images
Document Categories
Documents within selected category
Display per page:
Assessment Status
Notifications sent: NIRB Ltr to Parties re FEIS Technical Review and Submission of Technical review comments

2018-10-12 17:51:24

NIRB 123910/08MN053: Next steps in the NIRB’s Reconsideration and NWB Consideration of Baffinland’s “Phase 2 Development” Project Proposal and associated Water Licence Application


    Dear Parties:

    The Nunavut Impact Review Board (NIRB) and the Nunavut Water Board (NWB) are initiating the next steps in the coordinated process for Baffinland Iron Mines Corporation (BIMC or Proponent) “Phase 2 Development” proposal (the Project) and associated Water Licence Application (2AM-MRY1325) and are commencing the Information Request period.

    The NIRB respectfully requests that filing of Information Requests (IRs) be submitted on or before November 13, 2018. Submissions to the NIRB should be provided directly to info@nirb.ca or by fax to (867) 983-2594.

    Best regards,

    Andrea Omilgoitok
    Environmental Administrator

    Nunavut Impact Review Board
    29 Mitik Street
    P.O. Box 1360
    Cambridge Bay
    NU, X0B 0C0 Canada
    Phone: (867) 983-4600
    Toll Free: 1-866-233-3033
    Fax: (867) 983-2594
    Email: info@nirb.ca
    Web: www.nirb.ca

Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account