Project Dashboard

Status: ACTIVE REVIEW

  • NIRB File No:

    12MN001

  • Application No.:

    124148

  • Project Type:

    Mine Development

  • Project Name:

    Phase 2 Hope Bay Belt Project

Applicant
Primary Contact
External Links

Phase 2 Hope Bay Belt Project

Assessment Phase / Activity
  • Started application review 2011-09-15
  • Technical advisor assigned 2016-01-29
  • DEIS: Issue Decision on Exceptions from Review 2016-06-24
  • DEIS: Issue Decision on Exceptions from Review 2016-06-24
  • DEIS: Ltr to Parties Re Proposed submission date of DEIS 2016-11-10
  • DEIS: Ltr to Parties Re Proposed submission date of DEIS 2016-11-25
  • DEIS: Issued Notice Re Receipt of Draft EIS and Internal Confomity Review 2016-12-28
  • Internal Review: Information Request Period started 2017-02-24
  • Internal Review: Information Package to Proponent and Other Parties sent 2017-02-27
  • Technical Review: Commence Technical Review Period 2017-05-18
  • PHC: NIRB Notice to Parties re: Draft Pre-Hearing Conference Agenda 2017-05-31
  • Technical Review: Proponent Opportunity to Respond to Technical Review Comments Received 2017-06-05
  • PHC: NIRB Notice to Parties re: Final Pre-Hearing Conference Agenda 2017-06-02
  • Technical Review: NIRB ltr to Mayor Re Opening Remarks 2017-06-02
  • Technical Review: Proponent Opportunity to Respond to Technical Review Comments Received 2017-06-07
  • NIRB Notice to parties of comments received on Draft Commitment List 2017-06-16
  • Technical advisor assigned 2017-06-22
  • Technical advisor assigned 2017-06-22
  • PHC: Final List of Commitments issued 2017-06-26
  • PHC: PHC Report Issued 2017-07-21
  • NIRB Ltr to Proponent re anticipated Submission of FEIS date 2017-11-15
  • NIRB Ltr to Proponent re anticipated Submission of FEIS date 2017-12-04
  • Sent Notification to Parties 2017-12-08
  • FEIS: FEIS Document received 2017-12-21
  • NIRB Ltr to Parties re FEIS technical Review Period and submission of technical review comments. 2018-01-17
  • Final Hearing: Request for Intervenors completed 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • NIRB Ltr to Parties re community representatives 2018-02-28
  • Final Hearing: Final Written submissions completed 2018-03-20
  • NIRB Ltr to Proponent re Opportunity to Respond to Final Written Submissions 2018-03-20
  • NIRB Notice to Parties re: Draft Final Hearing Agenda 2018-04-06
  • Sent Notification to Parties 2018-04-16
  • NIRB Notice to Parties re: Final Hearing Agenda 2018-04-20
  • Technical Review: NIRB ltr to Mayor Re Opening Remarks 2018-04-24
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-04-24
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-04-24
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-04-27
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-04-27
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-04-30
  • NIRB Notice to Parties re Proponent Response to Final Written Submissions 2018-05-04
  • NIRB Notice to Parties re receipt of Final Written Submissions 2018-05-07
  • NIRB issues Notice re close of final hearing and online availability of final hearing exhibits 2018-05-15
  • NIRB Notice to Parties re Final Hearing Transcripts 2018-06-04
Region
  • Kitikmeot
Project Images
Assessment Status
Notifications sent: NIRB Notice to Parties re Final Hearing Transcripts

2018-06-04 12:30:27

NIRB 124148 / 12MN001: Public Hearing Transcripts now available from the NIRB's Public Hearing of TMAC's Phase 2 Hope Bay Belt Project


    Dear Parties,

    Please be advised that the official transcripts from the public hearing for the Nunavut Impact Review Board's (NIRB or Board) review of TMAC Resources Inc.’s (TMAC) Phase 2 Hope Bay Belt Project (NIRB File No. 12MN001) can be obtained from the NIRB's online public registry at www.nirb.ca by using any of the following search criteria:

  • Project Name: Phase 2 Hope Bay Belt Project
  • NIRB File No.: 12MN001
  • Application No.: 124148
  • Document ID No.: 317989 through 317993

    If you have any questions or concerns, feel free to contact Kofi Boa-Antwi, Technical Advisor II,, directly at (867) 983-4616 or by email at kboaantwi@nirb.ca.

    Best regards,

    Andrea Omilgoitok
    Environmental Administrator

    Nunavut Impact Review Board
    P.O. Box 1360 (29 Mitik)
    Cambridge Bay, NU, X0B 0C0
    Phone: 867-983-4600
    Toll Free: 1-866-233-3033
    Fax: 867-983-2594
    E-mail: info@nirb.ca
    Web: www.nirb.ca

Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account