Project Dashboard

Status: ACTIVE MONITORING

  • NIRB File No:

    03MN107

  • Application No.:

    124588

  • Project Type:

    Mine Development

  • Project Name:

    Meadowbank Gold Project

Applicant
  • Agnico-Eagle Mines Ltd., Stephane Robert
  • Agnico-Eagle Mines Ltd., Stephane Robert
  • P.O. Box 540, Baker Lake, NU X0C 0A0, Phone: 819-763-0229, Email: stephane.robert@agnico-eagle.com
  • ,
  • stephane.robert@agnicoeagle.com
Primary Contact
Regulatory Authorities
External Links

Meadowbank Gold Project

Assessment Phase / Activity
  • Started project monitoring 2005-09-14
  • Technical advisor assigned 2016-01-29
  • Notice to Parties re Comments on Draft Hearing Agenda 2016-04-20
  • NIRB Notice to Parties re Final Hearing Transcripts 2016-04-20
  • NIRB Ltr to Minister(s) re Final Hearing Report 2016-04-20
  • NIRB Received Report From Proponent 2016-04-28
  • NIRB Received Minister’s decision re Final Hearing Report 2016-07-28
  • NIRB Notice to Parties re Project Certificate Workshop 2016-07-29
  • NIRB Site Visit: Notice of Visit to RIA sent 2016-08-02
  • Received Project Licences, Permits and Authorizations from AAs 2016-08-02
  • NIRB Notice to Parties re Project Certificate Workshop 2016-08-10
  • NIRB Notice to Parties re Project Certificate Workshop 2016-08-11
  • NIRB Issues Amended Project Certificate to Proponent 2016-08-12
  • NIRB Issues Amended Project Certificate to Proponent 2016-08-12
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2016-11-04
  • NIRB Notice to Parties re Proponent Response received 2016-12-15
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-04
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2017-04-06
  • NIRB Ltr to Parties requesting comments on report. 2017-06-26
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-07-26
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-08-08
  • NIRB Issues notification of planned site visit 2017-08-08
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2017-08-15
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-16
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-01-25
  • NIRB Notice to Parties re Proponent response received 2018-01-25
  • NIRB Ltr to Proponent re Conformity Determination required 2018-01-31
  • Send Notification to Parties 2018-02-15
  • NIRB issues Notification to Proponent re Reporting Requirements Reminder (this is done annually) 2018-04-30
  • NIRB Received Report From Proponent 2018-05-10
  • NIRB Ltr to Parties requesting comments on report. 2018-05-17
  • NIRB Ltr to Parties requesting comments on report. Extended 2018-06-04
  • NIRB Ltr to Parties requesting comments on report. Extended 2018-06-22
  • NIRB Ltr to Parties requesting comments on report. 2018-08-09
  • NIRB issues notice of community information sessions 2018-08-09
  • NIRB Issues Monitoring Report and Recommendations for Proponent 2018-11-07
  • NIRB Issues Monitoring Report and Recommendations to Responsible Authorities 2018-11-21
  • Technical advisor assigned 2018-11-21
  • Technical advisor assigned 2018-11-21
  • NIRB Issues Monitoring Report and Recommendations to Responsible Authorities 2018-12-03
  • Send Notification to Parties 2018-12-11
  • NIRB Notice to Parties re Proponent response received 2018-12-18
  • NIRB Notice to Parties re Responsible Authority Response Received 2018-12-18
  • NIRB Notice to Parties re Proponent Response received 2019-01-14
  • Received Project Licences, Permits and Authorizations from RAs 2019-02-19
  • NIRB Ltr to Parties requesting comments on report. 2019-04-29
  • NIRB Ltr to Parties requesting comments on report. 2019-05-15
  • NIRB Ltr to Parties requesting comments on report. 2019-05-29
  • NIRB Notification to Parties Comments Received 2019-05-29
  • NIRB Ltr to Proponent Opportunity to Respond to Comments 2019-06-19
Region
  • Kivalliq
Project Images
Document Categories
Documents within selected category
Display per page:
Display per page:
Display per page:
Assessment Status
Notifications sent: NIRB Ltr to Proponent Opportunity to Respond to Comments

2019-05-29 18:27:17

NIRB 124588/03MN107 & 124683/16MN056: Opportunity to Address Comments Received for Agnico Eagle's Meadowbank Gold Mine Project and Whale Tail Pit Project 2018 Annual Monitoring Report


    29-May-2019

    Dear Parties,

    On April 10, 2019 the Nunavut Impact Review Board (NIRB or Board) received Agnico Eagle Mines Limited's (Agnico Eagle) Meadowbank Gold Mine Project and Whale Tail Pit Project 2018 Annual Monitoring Report (2018 Annual Report) and on April 12, 2019 the NIRB requested that interested parties review the 2018 Annual Report and provide comments.

    The NIRB would like to provide Agnico Eagle with the opportunity to address these comments prior to the completion of the NIRB’s Monitoring Officer Report, and requests that a response be provided directly to the NIRB by June 19, 2019.

    All documentation associated with this project proposal is available online from the NIRB's public registry at www.nirb.ca/project/124588 or www.nirb.ca/project/124683.

    Should you have any questions or require clarification regarding the NIRB’s monitoring of the Meadowbank Gold Mine Project or the Whale Tail Pit Project, please contact Erin Reimer, Technical Advisor I, directly at ereimer@nirb.ca or contact Sophia Granchinho, Manager, Impact Assessment at sgranchinho@nirb.ca.

    Best regards,

    Andrea Omilgoitok
    Environmental Administrator

    Nunavut Impact Review Board
    P.O. Box 1360 (29 Mitik)
    Cambridge Bay, NU, X0B 0C0
    Phone: 867-983-4600
    Toll Free: 1-866-233-3033
    Fax: 867-983-2594
    E-mail: info@nirb.ca
    Web: www.nirb.ca

Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account