Assessment Phase / Activity
  • Started application review 2016-09-09
  • Scoping: Notice of Dates and Location of Community Visits sent 2016-09-22
  • Scoping: Notice of Dates and Location of Community Visits sent 2016-10-04
  • Scoping: Comments re Draft Scope Received 2016-10-12
  • Scoping: Notice of Dates and Location of Community Visits sent 2016-10-19
  • Scoping: Final Scope issued 2016-11-10
  • DEIS: Ltr to Parties Re Proposed submission date of DEIS 2016-11-23
  • Scoping: NWB-NIRB Coordinated Process: Correspondence and Process Map Distributed 2016-11-25
  • Scoping: Final Scope issued 2016-12-06
  • Scoping: NWB-NIRB Coordinated Process: Correspondence and Process Map Distributed 2016-12-19
  • Internal Review: Information Package to Proponent and Other Parties sent 2016-12-23
  • Internal Review: Information Package to Proponent and Other Parties sent 2017-01-17
  • Scoping: Final Scope issued 2017-01-20
  • Technical Review: 60-day period started 2017-01-27
  • Internal Review: Received Response from Proponent and Other Parties 2017-03-03
  • PHC: NIRB Notice to Parties re: Draft Pre-Hearing Conference Agenda 2017-03-30
  • NIRB Issues Correspondence requesting Proponent Response to Technical Review Comments. 2017-04-11
  • PHC: NIRB Notice to Parties re: Final Pre-Hearing Conference Agenda 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB Issues Correspondence to Parties Re Soliciting Community Representatives 2017-04-21
  • Technical Review: NIRB ltr to Mayor Re Opening Remarks 2017-04-24
  • PHC: NIRB Notice to Parties re: Final Pre-Hearing Conference Agenda 2017-04-24
  • Technical Review: NIRB ltr to Mayor Re Opening Remarks 2017-04-24
  • Technical Review: Proponent Opportunity to Respond to Technical Review Comments Received 2017-04-25
  • PHC: NIRB Received Presentations and Materials from Proponent and Parties Re: Technical Meeting 2017-04-27
  • PHC: NIRB Received Presentations and Materials from Proponent and Parties Re: Technical Meeting 2017-05-01
  • PHC: Final List of Commitments issued 2017-05-02
  • NIRB Notice to parties of comments received on Draft Commitment List 2017-05-25
  • PHC: PHC Report Issued 2017-06-08
  • PHC: Final List of Commitments issued 2017-07-06
  • Sent Notification to Parties 2017-07-17
  • Final Hearing: Request for Intervenors in progress 2017-07-17
Region
  • Kivalliq
Project Images
Assessment Status
Notifications sent: Final Hearing: Request for Intervenors in progress

2017-07-17 17:59:43

NIRB 124683/16MN056: Notice of Final Hearing and Intervenor Application Deadline for the NIRB’s Review of Agnico Eagle’s Whale Tail Pit Project Proposal


    Dear Parties:

    Please find enclosed the Notice of Final Hearing for the Nunavut Impact Review Board’s (NIRB or Board) Review of Agnico Eagle Mines Ltd.’s (Agnico Eagle or Proponent) “Whale Tail Pit” Project Proposal (NIRB File 16MN056; “the Project”).

    The enclosed Notice of Hearing provides direction to parties wishing to apply for formal intervenor status for the hearing proceedings. For these potential intervenors, the Board requires the completion of an Application Form to request intervenor status (enclosed) to be filed with the Board on or before July 24, 2017.

    A copy of the notice has also been posted online to the NIRB’s public registry (with translated copies to follow) at www.nirb.ca and may be accessed by using any of the following search criteria:
     Project Name: Whale Tail Pit
     NIRB File No.: 16MN056
     Application No.: 124683

    Should you have questions regarding the upcoming Final Hearing for the NIRB’s consideration of the Whale Tail Pit project, including the NIRB’s Rules of Procedure and intervenor status applications, please contact Sophia Granchinho, Manager, Impact Assessment directly at sgranchinho@nirb.ca or by phone at (867) 857-4829.

    Best regards,

    Natasha Lear
    Environmental Administrator

    Nunavut Impact Review Board
    P.O. Box 1360 (29 Mitik)
    Cambridge Bay, NU, X0B 0C0
    Phone: 867-983-4600
    Toll Free: 1-866-233-3033
    Fax: 867-983-2594
    E-mail: info@nirb.ca
    Web: www.nirb.ca

Comment Form for NIRB Screenings

We appreciate your feedback/input. However you are currently not registered on the site (or your session has expired).

Registering for an account takes only moments and will provide you with more options/opportunities to participate in the NIRB process...

Register an Account